Reply from Dutch on Feb 22 at 6:30 PM That depends on the customer requested delivery date. If the date of 5/1/12 was a result of forward planning due to lack of availability (i.e. the customer requested the material earlier than that), then an early arrival of stock will lead rescheduling to attempt to meet the customer's required date. Unless you checked the "Fix date/qty"-flag of course. Hope this helps. Regards, Dutch
| | | ---------------Original Message--------------- From: SusanS Sent: Wednesday, February 22, 2012 4:55 PM Subject: Rescheduling Updating the ATP Sate Does rescheduling update the ATP date if material is received in before the proposed ATP date? For example, material x at the time of order entry was not available and had an ATP date of 5/1/12. The material was received in early and had a received date of 3/1/12. When rescheduling runs, will the schedule line update from 5/1 /12 to 3/1/12? | | Reply to this email to post your response. __.____._ | _.____.__ |