RE:[sap-log-sd] Rescheduling Updating the ATP Sate

Reply from Dutch on Feb 22 at 6:30 PM
That depends on the customer requested delivery date. If the date of 5/1/12 was a result of forward planning due to lack of availability (i.e. the customer requested the material earlier than that), then an early arrival of stock will lead rescheduling to attempt to meet the customer's required date. Unless you checked the "Fix date/qty"-flag of course.
Hope this helps.
Regards,
Dutch

---------------Original Message---------------
From: SusanS
Sent: Wednesday, February 22, 2012 4:55 PM
Subject: Rescheduling Updating the ATP Sate

Does rescheduling update the ATP date if material is received in before the proposed ATP date? For example, material x at the time of order entry was not available and had an ATP date of 5/1/12. The material was received in early and had a received date of 3/1/12. When rescheduling runs, will the schedule line update from 5/1 /12 to 3/1/12?

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Dutch  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__