RE:[sap-log-sd] Scope of Check Availability

Posted by BobLSchmidt
on Dec 7 at 11:27 AM
Relevancy is a matter of opinion. Prior ATP rules required that all inventory be available before a delivery is created. The current ATP rule creates the delivery regardless of available inventory - it then creates transfer orders as the inventory becomes available. As a result we do not want any dates to change.

---------------Original Message---------------
From: Bigsta
Sent: Wednesday, December 07, 2011 10:18 AM
Subject: Scope of Check Availability

Is there any point in changing the checking rule if you want to keep the current Schedule line dates? If you don't want to reschedule the orders then changing the rule is surely irrelevant.