When I run in the foreground it works. I run MD01 then MD40 collectively. However, a batch job runs 3 times a day. The MRP list in MD06 is not updating with new information. Example: Planned order was converted to process order. Run MRP and MPS and it remains as a planned order in MD06 (only for "some" materials). MD04 and MD07 is correct (since it is dynamic).
| | | ---------------Original Message--------------- From: R. N. Wilhite Sent: Tuesday, November 01, 2011 12:44 PM Subject: Planned Orders and Purch Reqs are not Deleting Sounds like you are running it in the background. Try running it in the foreground and see if anything changes. Neal | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight SAP BusinessObjects: Dashboards and Analytics. Learn more about this Toobox.com Marketplace online course. _.____.__ |