Sounds like you are running it in the background. Try running it in the foreground and see if anything changes. Neal
| | | ---------------Original Message--------------- From: Robin Osborne Sent: Tuesday, November 01, 2011 12:38 PM Subject: Planned Orders and Purch Reqs are not Deleting The problem is actually a bit different then originally reported. It appears that MD06 is not updating with the new MRP list after MRP/MPS batch job is finished. MD04, of course, reflects real time information and MD06 is only as current as the last MRP/MPS run. However, the batch jobs are running, the MRP list is created, but the changes are not reflected (i.e., planned order converted to process order) is not updating. | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | R. N. Wilhite SAP Logistics Sales and Distribution Helper