Re: [sap-log-sd] Cycle Counts Report

Reply from neobat on Mar 2 at 1:51 PM
try MI20 or MI21

---------------Original Message---------------
From: Gustavo Schmidt
Sent: Friday, March 02, 2012 1:30 PM
Subject: Cycle Counts Report

HI guru,

I would like to have a report that captives the materials are not counted in the cycle counts process. Per example we counted all the A items every 30 days, B items every 90 days, and C items every 180 days. I tried to ran MIDO but did not work. Any suggestion?

In advance your help is appreciated.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.