RE:[sap-log-sd] Scope of Check Availability

Posted by Dutch
on Nov 30 at 3:52 PM
Hi Bob,
This means that all schedule lines for the material/plant combination are confirmed. There is a checkbox in V_V2 ("Unconfirmed documents required") that you can deselect if you want to take orders into considerations that are all confirmed.

If there are some sales orders for which you do not want to rescheudle the dates, select the check box "Fixed date/quantities" on line item level. These lines will be disregarded by the rescheduling program.
Good luck,
Dutch

---------------Original Message---------------
From: Bob Schmidt
Sent: Tuesday, November 29, 2011 8:35 AM
Subject: Scope of Check Availability

We have recently made a change to our way of doing business. As a result many of our sales orders exist with an out-of-date Availability Check/Checking Rule. These orders are scheduled out into the future and would not self-purge in the near future. Is there a way I can update the scope of check for these sales orders?

Thank you

Bob Schmidt
Operations

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Dutch
SAP Logistics Sales and Distribution Helper

Posted helpful replies on 5 threads in a group to earn a Bronze Achievement
Popular White Papers

In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__