Hi ChrisO, You have mentioned "Put the order on with a delivery date that's beyond the planning horizon. MRP should then ignore it." Where can I see / set my planning horizon? Please explain your above comment. Many thanks!
| | | ---------------Original Message--------------- From: ChrisO Sent: Friday, December 09, 2011 10:55 AM Subject: Block the Order from MRP There are a few workarounds. Put the order on with a delivery date that's beyond the planning horizon. MRP should then ignore it. When the customer's credit is agreed, the desired date of delivery can then be entered in the sales order and MRP will tell you what's possible re delivery dates and quantities. Or put the order on as a quotation (T-code VA21), which doesn't pass the requirements on to MRP. When the order is OK to transfer to production, you create a new standard order with reference to the quotation. MRP will then tell you what's possible re delivery dates and quantities. Hope this helps, ChrisO | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Typewriter SAP Logistics Sales and Distribution Helper
Posted helpful replies on 50 threads in a group to earn a Silver Achievement Popular White Papers In the Spotlight _.____.__ |