Hi Gurus,

a) While Saving the sales order the system gives message that complete following elements:
1) WBS Element
2) Profit Segment

Please guide the setting for above two elements so that i can complete sales order.

b) How to maintain Shipping Point in Sales Order -

In Sales order the system is not Shipping Point.
I have done the setting in MMR, CMR plz guide where else the setting has to be done.

Thanks
Ashish