Re: [sap-log-sd] Material determination and availability check in this way...

Posted by Ash
on May 13 at 11:04 AM
HI ! ...

This kind of scenario is not maintained in material determination ,well if
the client requirement is to swap material based on the stock number and
availability than it will require some sap program to maintained or some
kind of re engineering enhancement is required to fulfill the typical
business process ...
As you know Material Determination is done to swap the material .....In your
case after the material A stock overs ,the system should automatically
replace or swap to Material B ....so for this kind of scenario you need to
put the condition saying that the system should use the material B once the
stock of Material A gets over ....looks like you want to swap the material
based on stock limitations.....

please let me know if there is any such standard scenario or any process
which equal to such functionality in SAP.....

---------------Original Message---------------
From: Peter M
Sent: Friday, May 13, 2011 7:58 AM
Subject: Material determination and availability check in this way...

Thanks but it is not answer for my question :) You explained me how material determination works - I know (more or less) how it work - the question was - it is possible to set up material determination in this way thay NOTHING HAPPEN as long as material A is available and system will propose new material only if material A in not available. Now system propose me material B or C even if A is available and I don't want it.

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Popular White Papers

In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT
_.____.__